Connect with us

Community

Work on the 64th Street Softball Field to Be Delayed

Improvements to the softball field at 64th Street that had been approved on March 13th, 2019 are set to be delayed by sixty days. During…

Published

on

Improvements to the softball field at 64th Street that had been approved on March 13th, 2019 are set to be delayed by sixty days.

During the work, some issues arose that prompted the engineer and contractors to agree upon an extension of the project. Some of the cited reasons for the delay include an extensive amount of rock excavation for the drainage basin in the parking lot, relocation of an on-site PSE&G pole, fabrication time for bleachers, and more.

Because of these unanticipated issues, the engineers and contractors had agreed to the sixty days. This was made into a proposal to the Board of Commissioners and was agreed upon at the Board of Commissioners meeting held on June 12th.

The improvements to the softball field are scheduled to be completed now on August 6th, 2019.

Continue Reading
Advertisement